一、安裝前準備工作
1、 Preparation work before installation
設備選型核查
Equipment selection verification
在安裝前必須嚴格核對除塵器型號規(guī)格與水泥罐倉的匹配性,包括處理風量、過濾面積等關鍵參數(shù),確保設備性能滿足工況需求。同時需檢查設備外觀是否完好,內部濾袋等核心部件有無運輸損傷。
Before installation, it is necessary to strictly check the compatibility between the dust collector model and specifications and the cement tank compartment, including key parameters such as processing air volume and filtration area, to ensure that the equipment performance meets the requirements of the working conditions. At the same time, it is necessary to check whether the appearance of the equipment is intact and whether there is any transportation damage to the core components such as the internal filter bag.
工具材料準備
Preparation of tools and materials
安裝需配備完整的工具套裝:包括不同規(guī)格的扳手套裝(8-19mm)、電動螺絲刀、水平儀、密封膠槍等專業(yè)工具。材料方面需準備耐高溫密封膠、304不銹鋼螺栓組(含平墊彈墊)、防爆電氣接線端子等。
Installation requires a complete set of tools, including wrench sets of different specifications (8-19mm), electric screwdrivers, level gauges, sealant guns, and other professional tools. In terms of materials, it is necessary to prepare high-temperature resistant sealant, 304 stainless steel bolt sets (including flat pads and spring washers), explosion-proof electrical wiring terminals, etc.
現(xiàn)場環(huán)境準備
On site environment preparation
安裝區(qū)域需進行徹底清理,使用工業(yè)吸塵器清除罐倉頂部積塵。設置隔離警戒區(qū),避免交叉作業(yè)影響安裝質量。準備防雨防塵臨時遮擋設施,確保安裝過程不受天氣影響。
The installation area needs to be thoroughly cleaned, using an industrial vacuum cleaner to remove dust from the top of the tank compartment. Set up isolation and warning areas to avoid cross operation affecting installation quality. Prepare temporary shelter facilities for rain and dust prevention to ensure that the installation process is not affected by weather.
二、安裝流程
2、 Standardized installation process
定位測量
Positioning measurement
采用全站儀進行精確定位,根據(jù)罐倉結構CAD圖紙確定除塵器安裝坐標。需考慮檢修空間要求(建議保留≥800mm環(huán)形通道),并避開倉頂安全閥等關鍵部件。
Using a total station for precise positioning, determine the installation coordinates of the dust collector based on the CAD drawings of the tank structure. Consider the maintenance space requirements (it is recommended to retain a circular channel of ≥ 800mm) and avoid key components such as the safety valve on the top of the warehouse.
支架安裝
Bracket installation
選用δ=8mm碳鋼支架,采用M16化學錨栓固定。安裝時使用激光水平儀校準,水平度偏差需控制在3‰以內。焊接部位需做防銹處理,并完成24小時承重測試。
Choose a carbon steel bracket with δ=8mm and fix it with M16 chemical anchor bolts. During installation, a laser level should be used for calibration, and the horizontal deviation should be controlled within 3 ‰. The welding area needs to undergo rust prevention treatment and complete a 24-hour load-bearing test.
管道連接
Pipeline connection
(1)進氣管道采用法蘭連接,石棉墊片需做浸油處理
(1) The intake pipeline adopts flange connection, and the asbestos gasket needs to be treated with oil immersion
(2)出風管道安裝膨脹節(jié)補償熱位移
(2) Installation of expansion joints to compensate for thermal displacement in the air outlet duct
(3)所有接口需進行氣密性檢測(0.05MPa保壓測試)
(3) All interfaces need to undergo air tightness testing (0.05MPa pressure holding test)
主體安裝
Main installation
吊裝時使用專用平衡梁,就位后采用扭矩扳手緊固螺栓(扭矩值參照GB/T3098.1)。最終檢測垂直度偏差≤2mm/m。
Use a dedicated balance beam during lifting, and tighten the bolts with a torque wrench after positioning (torque values refer to GB/T3098.1). The final verticality deviation is ≤ 2mm/m.
電氣安裝
Electrical installation
(1)按IEC標準敷設阻燃電纜
(1) Lay flame-retardant cables according to IEC standards
(2)防爆區(qū)域需使用ExdⅡBT4等級電器元件
(2) Explosion proof areas require the use of Exd Ⅱ BT4 grade electrical components
(3)接地電阻測試值≤4Ω
(3) Grounding resistance test value ≤ 4 Ω
本文由倉頂除塵器友情奉獻.更多有關的知識請點擊:http://m.liujianlin.cn我們將會對您提出的疑問進行詳細的解答,歡迎您登錄網(wǎng)站留言.
This article is a friendly contribution from the pneumatic conveying system For more information, please click: http://m.liujianlin.cn We will provide detailed answers to your questions. You are welcome to log in to our website and leave a message